HOME / ISOMETRIC MAP / SENSITIVE OR PROTECTED AREA / WASTE MANAGEMENT / 10.0 CONTROL OF SOLID WASTE AND BIOMASS
10.0 CONTROL OF SOLID WASTE AND BIOMASS
5. Ensure all waste collection facilities are covered or sheltered to avoid generation of leachate and hinder wind -blown waste.
6. Provide a centralised waste collection facility on-site. Locate the centralised waste collection facility at an area that can be accessed easily by waste collection / haul truck.
7. Conduct waste collection activities at both the workers’ quarters and construction areas in a systematic manner by assigning a person responsible for collecting and transferring all waste to a centralised waste collection facility within the site.
8. Appoint a contractor licensed by Local Authorities to collect waste produced from the project site and disposed of at an approved dumping ground.
9. Conduct regular inspection on workers’ quarters and construction areas to maintain good housekeeping practices by workers.
10. Locate all waste collection facilities at a minimum distance of 30 meters from the top of the bank (of the nearest river or watercourse) or distance specified in the AEC / MD.
10.2 Biomass Waste Management
1. Prohibit the burning of biomass.
2. Locate all biomass at a minimum distance of 30 meters from the top of the bank (of the nearest river or watercourse) or distance specified in the AEC / MD. Refer to Figure 17.