7.0 CONTROL OF NOISE AND OPERATION TIMES
5. When probable, place high noise-emitting machinery at the furthest point from the receptor (Please refer to Figure 11 for an illustration of noise source allocation within a project site).
Figure 11: Illustration showing the allocation of the noise source from probable receivers.
6. Consider installing movable noise barriers when it is anticipated that high noise-emitting machinery such as piling machines are used on-site. Install the movable noise barrier as close as possible to either the noise source or the receiver, with no gaps or openings at the barrier joints to minimise noise disturbance to adjacent land users. Refer to Plate 22 for an example of a removable noise barrier.
Plate 22: Example of movable barrier used for mitigating noise from piling.
7. Refer to Appendix 1 for additional references on controlling noise from sites.